An almost 300-page report on the discovery of an underground void at Ripon Leisure Centre has been described as “sobering reading”.
In the report published by Stantec, the engineering firm details how the void was found during works on the centre’s new multi-million pound swimming pool and why further investigations and groundworks are now required.
It said initial studies suggest there has been a “significant deterioration” of the ground beneath the older half of the centre which was built in 1995 and like much of Ripon sits on gypsum deposits.
The report begins by looking at construction records which reveal several ground piles had failed during the build almost three decades ago.
Stantec said the piles were not driven deep enough into the ground and that it remains unclear why this happened as “many critical records” are missing.
Replacement piles were added during the build, the report said, but it is believed these were driven into partially-filled holes.
Fast-forward more than 20 years after construction was completed and a sinkhole opened up outside the centre in 2018.
A year later, the refurbishment plans and new pool were approved by Harrogate Borough Council despite some councillors raising “deep concerns” over ground stability.
These works began shortly after and Stantec’s report said it was in September 2020 when the void was found by construction crews.
This was investigated and all areas beneath the older building will now be examined in the New Year.
The report said the void is having a “limited impact” on the building but “will continue to degrade over time” without action.
During the strengthening works, the older half of the centre is likely to close for around six months when the council said it would look to provide gym facilities at a different venue in Ripon.
The closures will mean the centre – which was due to be refurbished and open its new pool earlier this year – will not fully reopen until mid-2022.
0